Joint kickoff: the meeting that prevents a messy start
A program starts messy when each group walks away with a different idea of “done.”
Sales hears promise. Delivery hears assumptions. IT hears architecture. Business hears outcomes. Ops hears risk.
Run one joint kickoff that converts all of it into work, proof, owners, and dates.
Joint Kickoff Template
- Use for: CTRM/ETRM + integrations + data + ERP touchpoints
- Duration: 90 minutes core + 60 minutes deep dive (optional)
- Chair: Program Lead (Client)
- Scribe: PMO / Delivery Manager
- Single source folder link: ______________________
1) Purpose
Convert promises into delivery reality.
By the end of this session, the room agrees:
- scope boundaries (in and out)
- the first “definition of done”
- evidence required each week
- owners for decisions and delivery
- next 10 working days plan
2) Attendees
Client (Business)
- Exec sponsor (COO / Head of Trading)
- Product owner(s): Trading, Scheduling/Logistics, Risk, Settlements, Finance
- Ops lead (Back office / Middle office)
Client (IT)
- Program lead
- Solution architect
- Data lead
- Integration lead
- Security / IAM lead
- Test lead
- Change lead
Vendor / SI
- Delivery lead
- Solution architect
- Data migration lead
- Integration lead
- Test lead
- Change lead
3) Pre-read pack
Keep it short. Keep it specific.
- Contract + SOW + assumptions/exclusions
- “What Sales Promised” list (one page)
- Current process map (BPMN or equivalent) for 3 critical flows
- Interface inventory (Top 20)
- Data scope: master data + transactional + history
- Test approach (draft)
- Cutover approach (draft)
4) Agenda (90 minutes core)
0–10 min: The load rating
Question: What must not break on day one?
- Day-one critical workflows (pick 3)
- Non-negotiables: controls, audit, segregation of duties, reporting cutoffs
- Constraints: board date, freeze periods, close windows, market deadlines
Output: “Day-one must work” list (3 items) + constraints list
10–30 min: Promise → backlog conversion
Put every promise into a backlog item that a builder understands.
For each promise, capture:
- backlog item name
- acceptance criteria (pass/fail)
- evidence (demo, test, runbook, report)
- owner (client / vendor)
- due date
Output: top 15 promises converted into backlog items
30–45 min: Roles and decision rights
No shared ownership. One name per call.
- go/no-go authority
- scope change authority
- data decisions authority (golden source, mapping rules)
- integration sign-off authority
- testing sign-off authority
Output: one-page RACI + decision log owner list
45–65 min: Evidence rules and weekly cadence
Kill status theatre early.
Weekly evidence minimum:
- 1 workflow demo (real screens, real data slice)
- 1 test snapshot (must-run flows, pass/fail)
- 1 operability artefact (runbook, monitoring, cutover step)
Output: weekly demo-first rhythm + evidence pack folder structure
65–80 min: Risks that bite first
Pick five. Write triggers as facts.
- data quality and mapping gaps
- interface dependencies and environments
- model trust (if forecasts/automation exists)
- controls/IAM gaps
- vendor pace vs board date
Output: top 5 risks with triggers, owners, dates
80–90 min: The next 10 working days
Leave with motion, not notes.
- next demo date and workflow
- next decision deadline (top 3)
- next evidence pack due date
- next cutover rehearsal milestone
Output: 10-day plan with owners and dates
Optional deep dive (60 minutes)
Use when CTRM + ERP + data scope is heavy.
A) Data and mapping (30 min)
- books, portfolios, products, instruments
- cost centres, legal entities, counterparties
- pricing curves, units, calendars
Output: mapping ownership + first dataset cut date
B) Integration and controls (30 min)
- market data, ETRM/CTRM, scheduling, EDI, banking
- IAM, roles, break-glass, audit logs
Output: top 10 interfaces with test window plan + IAM sign-off date
5) Heavy cargo pre-lift checklist (use as the metaphor anchor)
Treat your kickoff outputs like a lift plan.
- Load weight = scope (what sits in, what stays out)
- Rigging plan = dependencies (interfaces, data sources, environments)
- Banksman = chair (one person controls comms and stop calls)
- Hand signals = evidence rules (demo/test/runbook proves progress)
- Wind limits = constraints (freeze windows, market deadlines, close cycles)
- Stop-work rule = rollback trigger (facts, not hope)
6) Definition of Done (copy/paste block)
A deliverable counts as “done” only when all boxes tick.
- Working workflow demo recorded
- Must-run tests passed (or defects logged with owner + date)
- Runbook updated for the workflow
- Controls checked (roles, audit trail, approvals)
- Evidence stored in the pack folder
- Stakeholder sign-off captured (name + date)
Outcomes, risks, mitigations
Short outcome
Shared reality on scope, owners, and proof. Less “we didn’t know.”
Risk: kickoff becomes a slide show.
Mitigation: live conversion of promises into backlog items.
Long outcome
Fewer rework loops, calmer cutover, stronger board trust.
Risk: decisions stall in committees.
Mitigation: named decision owners + due dates in the log.
Unexpected outcome
Vendor behaviour changes when “done” requires evidence.
Risk: defensive posture.
Mitigation: keep it neutral. Evidence replaces opinion.
Five-step rollout
- Assemble the pre-read pack (one folder, one page of promises).
- Run the 90-minute joint kickoff using the agenda above.
- Publish the outputs within 2 hours: backlog, RACI, decision log, risks, 10-day plan.
- Start the weekly evidence cadence immediately (first demo booked before the call ends).
- Track micro-promises weekly (late rate, decision latency, evidence gaps).