Sales promised. Delivery shrugged. Fix the baton pass.
If you’ve ever heard “that wasn’t in scope” after a deal is signed, you’ve seen the baton drop.
In commodity trading, the closest analogy is a trade confirmation handed to settlements with missing fields. The front office thinks it’s done. Settlements can’t invoice. Claims start. The problem is not effort. The problem is the handover.
Digital transformation fails the same way: sales commitments stay as language, not work.
The Joint Handover that prevents drift
Run this once, early. Then reuse it at every phase gate.
Five steps
Inventory the promises (no interpretation).
List every commitment: features, integrations, timelines, support model, data migration, controls, reporting, training. Include assumptions and exclusions.
Translate promises into backlog items.
Each promise becomes: a backlog item, acceptance criteria, and proof (demo, test, runbook, report).
Name owners and due dates.
One owner per item (client, vendor, or shared). One due date. One “done” definition with evidence.
Expose dependencies and constraints.
Board date, freeze window, market data feeds, interface windows, ERP close cycles, audit gates. Put them on one critical path.
Lock the weekly proof rhythm.
No slide status. Demo-first. Evidence pack. Decisions closed in days, not steering cycles.
What execs should demand as outputs (one page)
- Promise register (what was sold)
- Backlog mapping (what will be built)
- Decision log (what must be decided, by when)
- Evidence rules (what counts as “done”)
- Named owners (client + vendor)