Decisions before commitments
Give every LNG option the same starting point
A comparison only helps when the reader can separate a better choice from a more generous set of assumptions.
I become suspicious of an options table when the preferred column seems to live in a kinder world.
The plant starts faster. Customers pay earlier. Backup supply appears when needed and carries very little cost when it is not. The competing option receives all the awkward assumptions.
Nobody needs to manipulate a spreadsheet for this to happen. Different people can build different columns, each using a reasonable view of their own proposal. Put the columns together and the committee is comparing several versions of the business.
The first task is to give every option the same starting position. Only then can the differences tell us something useful.
Separate the background from the change
Imagine an illustrative LNG startup decision. The owner can retain the current plan, fund selected reliability work, buy temporary cover or reduce early commitments. All four choices should begin with the same customer obligations and the same view of the unfinished work.
An option can change those facts, but it needs to explain how. Reliability spending may change the probability or consequence of an interruption if the technical evidence supports it. A commercial negotiation may move a delivery window if the customer is willing to agree. Neither improvement should arrive as a free assumption.
Keep a visible record of what each option changes, what it costs to make that change and what evidence supports the effect. This makes it possible to disagree about one assumption without losing the rest of the comparison.
It also exposes dependencies. An option that relies on both a faster ramp and an earlier customer receipt is asking the owner to accept two separate conditions. A favourable total can conceal how much of the answer depends on both going well.
Give the difficult case equal treatment
Run the same adverse operating situation through each choice. If the plant slips again, which deliveries remain protected? What payments continue? Where does a contractual right help, and where has the model assumed a right that has not been secured?
Equal treatment does not mean identical outcomes. The purpose of cover is to behave differently when original supply is unavailable. The purpose of a smaller commitment is to reduce exposure. The comparison should preserve those differences while holding unrelated assumptions steady.
Nor should “do nothing” receive a free pass. Retaining the current plan may still require completion spending and acceptance of customer exposure. It is a live option with consequences, not an empty column against which new spending looks expensive.
Show what would change the recommendation
I would rather see the point at which the preferred choice changes than a confident ranking with no explanation. Does a longer delay make more cover worthwhile? Does an earlier payment requirement make that cover unaffordable? Which uncertainty is worth resolving before committing?
The public PARALLEL LNG demonstration provides an illustrative worked decision that readers can question. The useful place to begin is the assumptions and alternatives, rather than the selected result. A live case needs the owner's actual obligations and operating evidence.
A fair comparison may still support the sponsor's original preference. It should make that preference easier to explain because the other choices were given a proper hearing.
Worked demonstration: https://implementary.tech/parallel-decision-demonstration/