Who funds the replacement LNG cargo
Buying the replacement LNG cargo does not cancel the first cargo's cash commitments.

In an illustrative delay, the replacement supplier wants payment before the original receipt arrives. Shipping and terminal obligations remain. Full cover protects delivery, but partial cover or revised customer terms may preserve more funding capacity.
Buying cover for a delayed LNG plant adds a new commercial transaction while the original project continues to consume money. The customer receipt may still be weeks away. The business now has two demands on cash that were previously expected to follow one another.
An annual margin comparison makes this overlap surprisingly easy to miss. I would put the payment calendar on the table before deciding how much cover to buy.
01Follow both commitments through the same weeks
Take an illustrative startup delay. The owner still needs to fund completion work and operating preparation. It also wants a replacement cargo to meet an early customer obligation. The cover supplier requires payment before the customer pays for delivery.
Build the cash position from those actual obligations. Include freight and any security required under the proposed arrangements. Keep receipts conditional where the business has not yet earned the right to them. If a financing facility is available only after documents are accepted, the interval before acceptance still needs funding.
The useful number is the amount the business has to carry at its tightest point, with a date attached. A positive total return at the end of the transaction does not explain how the owner gets through that week.
Then move the plant date again. Cover purchased for the first delay may leave another delivery exposed. It may also overlap with a new construction payment. The second delay belongs in the comparison even if nobody considers it the most likely outcome.
02Cover the obligation that matters
There is no requirement for every early delivery to receive the same response. One customer may have a workable alternative window. Another may have a more expensive shortfall consequence. A third commitment may still be open to negotiation.
The commercial team should identify what can change before treating the full cover volume as fixed. A smaller purchase could protect the hardest obligation while leaving room for the plant to establish a more dependable ramp. That choice has a cost too, including any customer concession or reduced sales value.
Targeted reliability work may address a different part of the problem. It cannot be credited with eliminating the need for cover unless the relevant operating evidence supports that assumption. Keep the cost of the work and the consequence of continued delay visible together.
03Three routes through the funding week
Here is a simplified funding comparison in USD millions. The original book still requires 4 on day 1 and 3 on day 8 under every route. No receipt arrives before day 15. There is no opening cash; the paying entity has 12 of drawable capacity. Full replacement cover costs 6 plus 1 of freight. Assume a smaller parcel is physically available and can protect half the delivery. Its purchase is 3, freight is 0.6 and the agreed concession on the rescheduled balance is 0.4. Rescheduling the entire customer delivery costs 1 and requires written agreement.
| Before the first receipt | Full cover | Half cover + agreed balance | Agreed reschedule |
|---|---|---|---|
| Original obligations retained | 7 | 7 | 7 |
| Replacement purchase | 6 | 3 | 0 |
| Extra freight | 1 | 0.6 | 0 |
| Customer concession | 0 | 0.4 | 1 |
| Peak funding required | 14 | 11 | 8 |
| Headroom against drawable 12 | Short 2 | 1 remaining | 4 remaining |
| Original window protected | Full delivery | Half; balance rescheduled | None; new window agreed |
Full cover protects the original window but exceeds the available funding by 2. The smaller parcel fits the funding envelope only if the customer accepts the changed balance and the parcel can actually be scheduled. A full reschedule uses less cash but is unavailable until the customer agrees. Silence cannot be modelled as consent.
This table resolves feasibility, not the final commercial ranking. Price the margin given up, remaining delivery exposure and cost of each concession next. If the customer refuses to move the window, the lower-cash routes disappear and the decision becomes additional drawable funding, different supplier terms or an explicitly approved shortfall response. Retain the original cargo and its later receipt in the model throughout.
04Give treasury a decision it can support
Treasury needs more than a request to “find the money”. It needs the payment dates, the draw conditions and the exposures the commercial team can still negotiate. That allows a useful discussion about volume, supplier terms and the order in which commitments are made.
Keep both cargo histories on one dated cash path. Approve the delivery protected, peak funding need and exit condition together, including what happens if both cargoes arrive.
Bring one real decision.
Start with the trading commitment, the feasible alternatives and the date a decision is needed. PARALLEL helps make the obligations, cash and operating consequences comparable.