Decision latency: the hidden schedule killer
A trader misses a pricing window for one reason: time.
The curve moves, the market prints a new reality, and the “approval” arrives after the chance has gone.
Digital delivery has the same killer. It is not code. It is not “complexity.” It is decision latency: the gap between a question being raised and a decision being made.
Board timelines turn that gap into damage. Internal teams feel overloaded. Vendors hide behind jargon. Everyone stays polite. Workstreams stall anyway.
What decision latency looks like in a commodity trading program
It usually shows up as green status with quiet drift:
- “We need to confirm the curve source” → nobody owns the call → pricing logic waits
- “Are we netting by counterparty or legal entity?” → Ops and Finance disagree → settlement build waits
- “Do we migrate legacy trades or re-book?” → risk appetite unclear → data and cutover wait
- “Is this an exception or the new process?” → BPMN not final → training and change stall
- “Can the vendor support this interface?” → vendor says “possible” → no evidence → build starts wrong
Each delay feels small. The combined effect turns a plan into a series of idle gaps.
Measure it. Then you can fix it.
Stop asking “Are we blocked?”
Start tracking how long you stay blocked.
The only metric you need
Decision latency = Decision made date/time − Question raised date/time
Track it for every decision that sits on the critical path.
Keep it simple:
- median latency (typical speed)
- worst-case latency (the schedule killers)
- count of open decisions older than 7 days
That single view changes behaviour fast. It forces ownership. It exposes where the program actually slows.
The decision log that replaces steering arguments
Use one shared log (sheet, board, or ticket list). No debate without it.
Fields:
- Decision statement (one sentence)
- Date raised
- Raised by (person)
- Decision owner (one person)
- Options (max 2)
- Recommendation (one line)
- Decision date (blank until done)
- Blocked workstreams (list)
- Evidence needed (what must be shown)
Rule: If a workstream is waiting, the decision must exist in the log. If it is not logged, it is not real.
Fixing decision latency in five steps
1) Class decisions by type
You only need three buckets:
- Business policy (how we run the business)
- Technical design (how we implement it)
- Risk / control (what we must prove)
This prevents the worst failure mode: technical teams waiting on business decisions that nobody recognises as business decisions.
2) Name the decision owner before you discuss the decision
Not “the steering committee.” Not “we.” One name.
If the owner cannot decide, they are not the owner.
3) Set a decision service level
Treat decisions like operational incidents:
- standard decisions: 48 hours
- high-risk decisions: 5 working days
- urgent decisions that block the critical path: next steering
When the SLA is missed, you escalate by default. No emotional drama. Just process.
4) Pre-wire decisions with evidence, not opinions
Every decision needs a minimum pack:
- impact on timeline (one line)
- impact on cost (one line)
- impact on controls (one line)
- recommended option and why
This helps business leaders decide without being forced into vendor language.
5) Close decisions in the room, not after the room
If the meeting ends with “we’ll take it away,” the program just bought another week of stall.
Close it live where possible. If not possible, record:
- owner
- deadline
- exact evidence required
- what work is blocked until the decision lands
Balanced reality: vendor latency and internal latency
Decision latency is not only “client side.”
Vendor-driven latency often comes from:
- unclear feasibility answers (“should be fine” with no proof)
- missing architecture owners
- “we need you to do training” used as a shield
Internal-driven latency often comes from:
- split decision rights across Front Office, Ops, Risk, Finance
- SMEs unavailable because of day jobs
- leaders reluctant to choose between two imperfect options
The fix is the same: log it, time it, assign it, close it.
Outcomes, risks, mitigations
Short-term outcome: Fewer stalled workstreams. Faster approvals. Cleaner weekly steering.
Risk: people feel exposed by the clock.
Mitigation: measure latency to fix the system, not blame individuals.
Long-term outcome: Governance becomes a rhythm: evidence → decision → action. Less rework late in the cycle.
Risk: decision owners avoid ownership.
Mitigation: link decision ownership to the critical path. If you block the path, you own the decision.
Unexpected outcome: Vendor behaviour improves. They bring proof sooner because “maybe” no longer survives contact with a timestamp.
A practical next step
If your program feels busy but slow, use a Reset Plan to lock actions, owners, dates, and vendor accountabilities, then run a weekly cadence where decision latency is reviewed like exposure.