Decisions are the real critical path

You can have 300 tasks “in progress” and still be dead in the water.

Because the thing that actually stops delivery is almost never a task.

It’s a decision that nobody wants to own. Or a decision that sits in a calendar black hole.

Here’s the scene you’ll recognise.

Monday stand-up. The devs are ready. The vendor says they can build. Your Jira board looks… optimistic.

Then someone asks, “Which booking model are we using for storage and transport?”

Silence. A few people talk around it. Somebody says, “We’ll take it offline.”

That “offline” decision becomes your real critical path.

Why trading teams get this faster than project teams

On a desk, you miss a nominations deadline and you don’t get a second chance.

Volume slips. Optionality disappears. You pay to unwind. You wear it.

In transformation, missing a decision date does the same thing. It just hides better.

Workstreams stall, then sprint. Testing compresses. Cutover gets spicy. People burn out.

The plan still claims you’re “80% done” because tasks moved. Reality says otherwise.

Pick a side

A Gantt chart without a decision lane is comfort theatre.

If your program is blocked, it’s usually blocked by one of these:

  • Business design decisions (process, controls, accounting treatment, booking model)
  • Data decisions (golden source, mapping ownership, reconciliation standard)
  • Risk decisions (security posture, segregation of duties, exceptions)
  • Cutover decisions (freeze windows, rollback triggers, comms authority)

Treat those as deliverables. Not “discussion topics.”

The Decision Calendar

This is the simplest tool that changes behaviour fast.

It forces clarity, ownership, and due dates. It also makes escalation clean.

Template

Copy/paste this into your program pack:

  • Decision ID
  • Decision
  • Needed by
  • Decision owner
  • Recommendation owner
  • Inputs required
  • Options (A/B/C)
  • Consequence if late
  • Evidence / artefact
  • Status
  • Next action + date

Fully worked example (realistic CTRM + ERP program data)

Assume a board-go-live target of 30 Jun 2026 and UAT start of 11 May 2026.

Decision ID Decision Needed by Decision owner Recommendation owner Inputs required Options (A/B/C) Consequence if late Evidence / artefact Status Next action + date
D-01 Target booking model for physical deals + storage + transport (incl. provisional pricing) 2026-02-06 Head of Trading Ops Lead BA Draft BPMN, sample deals, accounting policy constraints A) Standard template per commodity B) Separate by region C) Hybrid Config blocked; downstream test scripts invalid Signed BPMN + booking rules v1.0 At risk Pre-read issued 2026-02-03; decision meeting 2026-02-06
D-02 Accounting treatment + postings for inventory + MtM + accruals (CTRM ↔ ERP) 2026-02-13 CFO delegate / Financial Controller ERP Solution Lead Posting design, chart of accounts mapping, audit requirements A) ERP-led postings B) CTRM-led postings C) Split by product Reconciliation becomes manual; close process breaks Posting design doc + sample journal outputs Open Workshop 2026-02-10; sign-off 2026-02-13
D-03 Golden source for prices and curves (EU power, UK power, AU NEM, US ISO) 2026-02-20 Chief Risk Officer / Head of Risk Market Data Lead Vendor options, latency needs, controls A) Single vendor B) Regional mix C) Internal aggregation Intraday automation unreliable; disputes over “truth” Curve governance + source list + control checks Open Options paper 2026-02-17; decision 2026-02-20
D-04 Exception handling thresholds for intraday automation (when humans must intervene) 2026-03-06 Trading Head Quant/Algo Lead Backtesting results, risk limits, auditability needs A) Tight thresholds B) Moderate C) Dynamic Automation either spams humans or runs unsafe Threshold rules + audit trail design Open Replay test results 2026-03-03; decision 2026-03-06
D-05 Month-end and go-live freeze windows (what stops, when, who approves exceptions) 2026-03-13 CIO + COO Release Manager Settlement calendar, regulatory constraints, cutover plan A) Hard freeze B) Controlled changes C) Risk-based Late changes break settlement; cutover chaos Freeze policy + exception workflow Draft Exec review 2026-03-11; publish 2026-03-13
D-06 Cutover authority and rollback triggers (who calls stop/go) 2026-04-10 Program Sponsor Cutover Lead Dry-run results, rollback plan, comms plan A) Sponsor calls B) Cutover lead calls C) Joint authority Everyone argues at 2am; rollback too late Signed cutover runbook + storm-drill report Open Storm drill 2026-04-07; sign-off 2026-04-10

That table looks boring until you run it weekly.

Then it becomes the only thing people take seriously.

Build it in five steps

  • List the decisions that can block build, test, or cutover. If it can stall a workstream, it’s a decision.
  • Name the decision owner. One person. Not “the business.”
  • Set a “needed by” date that protects downstream work. Work backwards from UAT and cutover.
  • Define evidence. What proves the decision exists: signed BPMN, config screenshot, posting output, runbook.
  • Run a weekly decision review. 15–30 minutes. Decisions due next 2 weeks only. Escalate same day.

Outcomes, risks, mitigations

Short-term outcome: the program feels slower for a week because hand-waving stops.

Long-term outcome: delivery speed increases because fewer teams build on guesses.

Unexpected outcome: the calendar exposes a governance gap. The right people are not available.

Risk: owners dodge decisions or delegate without authority.

Mitigation: name a delegate with signing rights, and write escalation into the rhythm (same day, not next steering).

Next step if you want to turn this into a working plan

If your timeline is “fixed” but delivery keeps stalling, build a Reset Plan: actions, owners, dates, and vendor accountabilities, starting with a Decision Calendar like the one above.

Weekly Newsletter

Get the Weekly Implementary Insights Wrap Up PDF every Friday.

Privacy: We will not use your contact information for any purpose other than sending this Newsletter.
Unsubscribe anytime with one click from any email.
Published On: January 26th, 2026 / Categories: Transformation /