Earned vs burn: the chart that ends arguments
A voyage plan looks calm on paper. Then the fuel gauge drops faster than the miles tick up.
That is the program you run when the board date stays fixed, the internal team feels overloaded, and the vendor talks in a language your business does not use. People argue about status because nobody can agree on reality.
Earned vs burn ends that argument because it ties two things that matter to both Exec and IT:
- Burn: money and effort consumed
- Earned: verified delivery accepted (not “almost done”)
Define the two lines in plain language
Burn (cost consumed)
Count what you pay and what you burn internally:
- vendor invoices or time sheets (actuals, not forecast)
- internal effort on critical delivery work (approximate is fine; consistency matters more than precision)
- hard costs tied to the work (environments, tooling, data services)
Rule: track burn weekly. Do not “smooth” it.
Earned (value delivered)
Earned is not story-time. Earned is accepted deliverables.
Use a simple scoring model:
- total program = 100 points
- split those points across the critical path deliverables only
- earn points only when the deliverable meets your acceptance gate (demo + tests + operability proof)
- If a deliverable does not move the go-live, it gets 0 points. That forces focus.
The acceptance gate that makes “earned” real
Before you award points, ask:
- Does it run end-to-end for a real scenario?
- Do we have test evidence (pass/fail) for that scenario?
- Can Ops run it under pressure (runbook + owner + monitoring)?
If any answer is “no,” earned stays at zero for that item. Status stays a claim.
The chart that fits on one slide
Plot two cumulative lines by week:
- Cumulative burn ($)
- Cumulative earned (points)
Add one number at the top right:
- Earned/Burn ratio (points per $m or points per $100k, pick a scale that reads cleanly)
Interpretation in one sentence:
- When burn rises and earned flattens, the program buys activity, not delivery.
Five steps to build this in one week
- Lock the critical path (8–12 deliverables).
- Name them in business terms: “trade → risk → confirmation runs” beats “UAT progressing.”
- Weight each deliverable (points).
- Give bigger weights to items that unblock multiple teams (interfaces, data readiness, cutover rehearsal).
- Define evidence for each deliverable.
- One demo, one test report, one runbook excerpt. Links, not opinions.
- Track burn as actuals.
- Pull vendor actuals and rough internal effort. Keep the method consistent each week.
- Run steering on the chart, not the deck.
- Open with the two lines. Then ask only:
- “What earned points this week?”
- “What blocked earned?”
- “Which decision changes next week’s slope?”
What this changes in the room
Short-term outcomes
Faster alignment between Exec, IT, and vendor because the argument shifts from “how do we feel?” to “what got accepted?”
Earlier escalation when the program burns cash without moving the date
Risk: teams game the scoring.
Mitigation: tie points to evidence and acceptance gates, not self-reporting.
Long-term outcomes
Cleaner governance rhythm: evidence, decisions, actions
Better budgeting because burn has a real denominator (earned delivery), not just time elapsed
Risk: leaders demand precision and stall the setup.
Mitigation: start with “directionally right,” improve weekly.
Unexpected outcomes
Vendor language changes. They bring artefacts because the chart punishes vague updates.
Internal overload becomes visible. Low earned with high burn often signals SME bottlenecks and dependency churn.
If you need weekly momentum to go-live
If the program needs a steady cadence that keeps evidence, owners, and vendor commitments tight, Rescue Support runs the plan to go-live and keeps the earned-vs-burn view honest week after week.