Mini-guide: Measure decision latency weekly (like you track P&L)

Every delivery plan looks “tight” until it hits the real critical path:

decisions. In commodity and energy trading, waiting has a price. A wide bid‑offer, a missed nomination, a gate closure you can’t rewind. Project decisions work the same way. Delay turns into slippage, rework, and vendor theatre. This guide gives you a clean way to track “raised-to-decided” time and treat it as a KPI—across IT, the business, and the vendor.

1) What “decision latency” means

Decision latency = time from “question raised” to “decision made”.

Not time to write a deck. Not time to “socialise.” Not time to “circle back.”

Just:

  • Raised: someone asks for a decision that blocks work
  • Decided: an accountable owner chooses option A/B/C and logs it
  • Closed: the decision translates into work (backlog, config, test, comms)

2) Why it matters in trading platform delivery

Trading platforms fail in slow motion. The first crack looks small:

  • “We’re waiting on business rules.”
  • “We need vendor input.”
  • “Legal hasn’t reviewed.”
  • “Risk wants another pass.”

Then three weeks later it becomes:

  • UAT starts without a stable workflow
  • Data mapping “nearly done” stays “nearly done”
  • Cutover rehearsals run on assumptions
  • A board date turns into a negotiation

Point of view:

If you don’t track decision latency, you aren’t running a program. You’re running a feelings-based governance ritual.

3) The weekly cadence: 15 minutes, no excuses

Run this once per week (Friday works; Tuesday also works if Friday gets messy).

The agenda

  • Decisions raised this week (new): what entered the log?
  • Decisions decided this week (closed): what left the log?
  • Decision debt: what is overdue (past “required-by”)?
  • Top 3 stalls: which forum/owner/vendor queue causes delay?
  • One fix: what changes next week to reduce latency?

That’s it. No theatre. No status colours.

4) The decision log template (copy/paste)

Use this as your single source. A shared sheet beats ten side chats.

  • Decision ID:
  • Decision statement (one sentence):
  • Raised date:
  • Raised by (name/role):
  • Required-by date (the “gate closure”):
  • Decision owner (one name):
  • Decision forum (SteerCo / Design Authority / Risk / Ops):
  • Options presented (A/B/C):
  • Artefacts attached (links): (screens, config, BPMN, test evidence)
  • Dependencies blocked: (workstreams, vendor tasks, internal tasks)
  • Impact if late: (Time / Cost / Risk / Controls / Compliance)
  • Decision made (date):
  • Decision outcome (what we chose):
  • Next actions (3 bullets max):
  • Action owners + due dates:
  • Status: Open / Decided / Closed

5) The KPI pack (what you show leadership)

Put these six numbers at the top of the weekly update:

  • Open decisions (count)
  • New decisions raised (count)
  • Decisions closed (count)
  • Median latency (days)
  • P90 latency (days)
  • Overdue decisions (count)

Optional (but powerful):

  • Decision latency by forum (where decisions go to die)
  • Decision latency by owner (where accountability is fuzzy)
  • Decision debt value (open decisions blocking critical path items)

6) Worked example (realistic CTRM/ETRM + ERP program)

Context:

A global energy trader upgrades CTRM for power + gas, adds intraday automation workflows, and integrates to ERP for postings and accruals. Vendor runs build + integration. Internal teams own business rules, controls, and sign-off.

Decision log extract (sample)

ID Decision Raised Required-by Owner Forum Decided Latency Impact if late
D-014 AU NEM bidding: auto-submit thresholds + exceptions 6 Jan 10 Jan Head of Trading Ops Design Authority 13 Jan 7d Intraday workflow blocked
D-015 EU intraday: order types supported in v1 7 Jan 9 Jan Product Owner Design Authority 10 Jan 3d Build scope unclear
D-016 UK: exception process for gate-closure adjustments 8 Jan 12 Jan COO delegate SteerCo 20 Jan 12d Control gaps + rework
D-017 Market data: normalisation approach + fallback feed 9 Jan 13 Jan IT Lead Tech Authority 17 Jan 8d Pricing + P&L accuracy risk
D-018 ERP: posting granularity for realised/unrealised 9 Jan 14 Jan Finance Controller Finance Forum 14 Jan 5d Close process risk
D-019 Credit limits: pre-trade hard block vs soft alert 10 Jan 12 Jan Risk Lead Risk Forum 12 Jan 2d Regulatory/control exposure
D-020 Test env refresh: cadence + data masking method 12 Jan 13 Jan Vendor Test Lead Delivery Forum 13 Jan 1d UAT churn avoided

What the KPI pack shows that week

  • Closed: 7
  • Median latency: 5 days
  • P90 latency: 12 days
  • Overdue: 1 (D‑016 blew past required-by)

The punchline

The program didn’t “slip” because people worked slowly.

It slipped because the decision forum acted like a backlog grooming session, not a trading desk.

The fix was not another project manager. The fix was:

  • A twice-weekly Decision Authority (30 minutes, timed)
  • One-page option packs required 24 hours before forum
  • A fast lane rule: “If it blocks a critical-path build item, it gets a decision owner in 24 hours”

Next two weeks, median latency dropped from 5 days to 3 days (in this example), and the vendor stopped hiding behind “waiting on client” because the log named owners and dates.

7) How to cut decision latency (without starting a war)

For internal IT + business

  • Name one decision owner. Not a committee. One throat to choke, one throat to thank.
  • Write the decision in one sentence. If you can’t, you’re not ready.
  • Timebox options to three. More than three = avoidance with extra steps.
  • Tie required-by to a real gate. UAT start. Data freeze. Market cutover. Month-end.

For the vendor

  • No decision goes to forum without artefacts. Screens, config, BPMN, test evidence, or runbook excerpt.
  • No “blocked” status without a decision ID. If it’s not in the log, it’s not blocked.
  • No side-channel decisions. A decision made in a private chat is a future outage.

8) Five-step rollout across a live program

  • Start the decision log today (even if it’s ugly).
  • Backfill the last 10 “stalls” (the stuff everyone argues about).
  • Set SLAs by decision type (controls decisions faster than nice-to-have).
  • Run the first 15‑minute review and publish the six KPI numbers.
  • Fix the top bottleneck (forum cadence, missing option packs, unclear owner).

Weekly Newsletter

Get the Weekly Implementary Insights Wrap Up PDF every Friday.

Privacy: We will not use your contact information for any purpose other than sending this Newsletter.
Unsubscribe anytime with one click from any email.
Published On: January 29th, 2026 / Categories: Transformation /