Mini-guide: Measure decision latency weekly (like you track P&L)
Every delivery plan looks “tight” until it hits the real critical path:
decisions. In commodity and energy trading, waiting has a price. A wide bid‑offer, a missed nomination, a gate closure you can’t rewind. Project decisions work the same way. Delay turns into slippage, rework, and vendor theatre. This guide gives you a clean way to track “raised-to-decided” time and treat it as a KPI—across IT, the business, and the vendor.
1) What “decision latency” means
Decision latency = time from “question raised” to “decision made”.
Not time to write a deck. Not time to “socialise.” Not time to “circle back.”
Just:
- Raised: someone asks for a decision that blocks work
- Decided: an accountable owner chooses option A/B/C and logs it
- Closed: the decision translates into work (backlog, config, test, comms)
2) Why it matters in trading platform delivery
Trading platforms fail in slow motion. The first crack looks small:
- “We’re waiting on business rules.”
- “We need vendor input.”
- “Legal hasn’t reviewed.”
- “Risk wants another pass.”
Then three weeks later it becomes:
- UAT starts without a stable workflow
- Data mapping “nearly done” stays “nearly done”
- Cutover rehearsals run on assumptions
- A board date turns into a negotiation
Point of view:
If you don’t track decision latency, you aren’t running a program. You’re running a feelings-based governance ritual.
3) The weekly cadence: 15 minutes, no excuses
Run this once per week (Friday works; Tuesday also works if Friday gets messy).
The agenda
- Decisions raised this week (new): what entered the log?
- Decisions decided this week (closed): what left the log?
- Decision debt: what is overdue (past “required-by”)?
- Top 3 stalls: which forum/owner/vendor queue causes delay?
- One fix: what changes next week to reduce latency?
That’s it. No theatre. No status colours.
4) The decision log template (copy/paste)
Use this as your single source. A shared sheet beats ten side chats.
- Decision ID:
- Decision statement (one sentence):
- Raised date:
- Raised by (name/role):
- Required-by date (the “gate closure”):
- Decision owner (one name):
- Decision forum (SteerCo / Design Authority / Risk / Ops):
- Options presented (A/B/C):
- Artefacts attached (links): (screens, config, BPMN, test evidence)
- Dependencies blocked: (workstreams, vendor tasks, internal tasks)
- Impact if late: (Time / Cost / Risk / Controls / Compliance)
- Decision made (date):
- Decision outcome (what we chose):
- Next actions (3 bullets max):
- Action owners + due dates:
- Status: Open / Decided / Closed
5) The KPI pack (what you show leadership)
Put these six numbers at the top of the weekly update:
- Open decisions (count)
- New decisions raised (count)
- Decisions closed (count)
- Median latency (days)
- P90 latency (days)
- Overdue decisions (count)
Optional (but powerful):
- Decision latency by forum (where decisions go to die)
- Decision latency by owner (where accountability is fuzzy)
- Decision debt value (open decisions blocking critical path items)
6) Worked example (realistic CTRM/ETRM + ERP program)
Context:
A global energy trader upgrades CTRM for power + gas, adds intraday automation workflows, and integrates to ERP for postings and accruals. Vendor runs build + integration. Internal teams own business rules, controls, and sign-off.
Decision log extract (sample)
| ID | Decision | Raised | Required-by | Owner | Forum | Decided | Latency | Impact if late |
|---|---|---|---|---|---|---|---|---|
| D-014 | AU NEM bidding: auto-submit thresholds + exceptions | 6 Jan | 10 Jan | Head of Trading Ops | Design Authority | 13 Jan | 7d | Intraday workflow blocked |
| D-015 | EU intraday: order types supported in v1 | 7 Jan | 9 Jan | Product Owner | Design Authority | 10 Jan | 3d | Build scope unclear |
| D-016 | UK: exception process for gate-closure adjustments | 8 Jan | 12 Jan | COO delegate | SteerCo | 20 Jan | 12d | Control gaps + rework |
| D-017 | Market data: normalisation approach + fallback feed | 9 Jan | 13 Jan | IT Lead | Tech Authority | 17 Jan | 8d | Pricing + P&L accuracy risk |
| D-018 | ERP: posting granularity for realised/unrealised | 9 Jan | 14 Jan | Finance Controller | Finance Forum | 14 Jan | 5d | Close process risk |
| D-019 | Credit limits: pre-trade hard block vs soft alert | 10 Jan | 12 Jan | Risk Lead | Risk Forum | 12 Jan | 2d | Regulatory/control exposure |
| D-020 | Test env refresh: cadence + data masking method | 12 Jan | 13 Jan | Vendor Test Lead | Delivery Forum | 13 Jan | 1d | UAT churn avoided |
What the KPI pack shows that week
- Closed: 7
- Median latency: 5 days
- P90 latency: 12 days
- Overdue: 1 (D‑016 blew past required-by)
The punchline
The program didn’t “slip” because people worked slowly.
It slipped because the decision forum acted like a backlog grooming session, not a trading desk.
The fix was not another project manager. The fix was:
- A twice-weekly Decision Authority (30 minutes, timed)
- One-page option packs required 24 hours before forum
- A fast lane rule: “If it blocks a critical-path build item, it gets a decision owner in 24 hours”
Next two weeks, median latency dropped from 5 days to 3 days (in this example), and the vendor stopped hiding behind “waiting on client” because the log named owners and dates.
7) How to cut decision latency (without starting a war)
For internal IT + business
- Name one decision owner. Not a committee. One throat to choke, one throat to thank.
- Write the decision in one sentence. If you can’t, you’re not ready.
- Timebox options to three. More than three = avoidance with extra steps.
- Tie required-by to a real gate. UAT start. Data freeze. Market cutover. Month-end.
For the vendor
- No decision goes to forum without artefacts. Screens, config, BPMN, test evidence, or runbook excerpt.
- No “blocked” status without a decision ID. If it’s not in the log, it’s not blocked.
- No side-channel decisions. A decision made in a private chat is a future outage.
8) Five-step rollout across a live program
- Start the decision log today (even if it’s ugly).
- Backfill the last 10 “stalls” (the stuff everyone argues about).
- Set SLAs by decision type (controls decisions faster than nice-to-have).
- Run the first 15‑minute review and publish the six KPI numbers.
- Fix the top bottleneck (forum cadence, missing option packs, unclear owner).