One Decision Forum. One Log. Zero Side Deals.
A delivery playbook for CTRM/ETRM + ERP programs in commodity and energy trading
You don’t lose trading-platform programs because “the vendor is bad” or “IT is slow”.
You lose them because decisions leak.
A trader agrees to something with a vendor in a corridor. Finance changes a posting rule in a side email. Ops says “we’ll handle it in cutover” without stating how. Everyone feels progress… until the build hits a wall and the program starts paying interest on confusion.
This playbook stops the leak: one decision forum, one decision log, no side deals.
1) The rules
Rule 1 | If it’s a decision, it goes in the log.
No log entry, no decision. No exceptions.
Rule 2 | The log is the truth, not the slide deck.
Your status report can be green. Your log can be red. The log wins.
Rule 3 | Decisions need evidence.
A decision is not “we think”. It’s “here’s the artefact, here’s the owner, here’s the date”.
Rule 4 | Side deals become change requests.
If someone “promises” something outside the forum, it becomes a formal CR with cost/time/risk.
Rule 5 | A decision has an expiry date.
If a decision isn’t implemented by a defined date, it comes back to the forum.
2) The operating model
2.1 Decision taxonomy (keep it simple)
- Scope (what is in/out, and for which markets/commodities)
- Design (workflow, data model, integrations, controls)
- Data (sources, mapping, quality gates, ownership)
- Test (entry/exit criteria, defect triage rules, sign-off)
- Cutover/Go-live (runbook, rollback triggers, comms)
- Operating model & change (roles, handoffs, training, support)
2.2 Authority ladder (example)
- Forum can decide: items ≤ 5 business days impact and ≤ $50k equivalent effort, no regulatory/control change.
- Steering decides: anything above, plus anything affecting controls, audit posture, or go-live date.
- Board sponsor decides: anything that changes “why we’re doing this” or materially shifts benefits, risk appetite, or timeline commitment.
(Numbers are placeholders. Set your own thresholds once, then enforce them.)
2.3 Cadence (minimum viable)
- Decision Triage (15 min, 2x/week): confirm what is actually a decision; assign owner; set due date.
- Decision Forum (45–60 min weekly): make decisions or escalate them.
- Steering (60 min fortnightly): resolve escalations; approve trade-offs.
2.4 Attendance (balanced by design)
- Exec sponsor or delegate (chair)
- Business product owner (front office)
- Back office/ops lead (scheduling/settlement)
- Finance/controllership lead (ERP impact)
- IT delivery lead
- Architecture/integration lead
- Test lead
- Vendor delivery lead (not sales)
3) The artefacts
3.1 The 1-page Decision Brief (template)
Use this as the only “entry ticket” into the forum.
- Decision ID:
- Decision title:
- Why this matters now (1 sentence):
- Decision needed by (date):
- Owner (name/role):
- Context (3 bullets):
- Options (2–3) with trade-offs:
- Option A:
- Option B:
- Option C (if needed):
- Recommendation (1 line):
- Evidence (links): (config screenshot, mapping doc, test report, BPMN, runbook step, etc.)
- Impact summary:
- Time impact:
- Cost/effort impact:
- Risk/control impact:
- Change impact (training/process):
- Decision required from: Forum / Steering / Sponsor
- If we don’t decide: (real consequence, not drama)
3.2 The Decision Log (template fields)
This is the “single blotter”.
- ID
- Date raised
- Decision title
- Category (Scope/Design/Data/Test/Cutover/OM)
- Owner
- Due date
- Evidence link(s)
- Options captured (Y/N)
- Recommendation captured (Y/N)
- Status (Open / Ready / Decided / Implemented / Re-opened)
- Decision date
- Decision maker (Forum / Steering / Sponsor)
- Decision statement (one sentence)
- Implementation ticket(s) / work item(s)
- Change request ID (if any)
- Notes / rationale
- Comms sent (Y/N)
3.3 “No side deals” comms note (template)
Send once at program start; repeat when needed.
Decision hygiene notice
From today, all program decisions run through the Decision Log and weekly Decision Forum.
If you agree something outside that process, it’s treated as a request, not a decision, until it’s logged and approved.
This protects delivery, controls, and people’s time. If you need urgency, raise it in triage and we’ll fast-track it.
4) Worked example with realistic trading/ERP data
Below is a worked example (illustrative) from a global energy/commodity trading platform program with ERP integration. The structure is real. The numbers are realistic placeholders to show how it looks when it’s running properly.
Program context (example)
- Scope: Replace legacy CTRM, add power intraday controls, integrate with ERP for accounting and cost allocation
- Markets supported: EU intraday, AU NEM, UK, US
- Go-live commitment: end of Q2 (board date fixed)
- Delivery model: internal IT + vendor delivery + business SMEs
- Pain: decisions happening in side chats → reversals → rework
4.1 Example Decision Calendar (next 4 weeks)
| Week | Decisions that must close | Why it’s on the critical path |
|---|---|---|
| W1 | Time granularity standard (5/15/30 min), product hierarchy, posting model | Drives data model, interfaces, reporting, and test design |
| W2 | Market data sourcing approach, exception handling design, UAT entry criteria | Stops “demo-only” progress and forces testable definitions |
| W3 | Cutover approach per region, rollback triggers, support model | Prevents go-live chaos and midnight improvisation |
| W4 | Change freeze rules, training scope, final integration sign-offs | Protects operations and stabilises the platform |
4.2 Example Decision Log (realistic entries + numbers)
| ID | Title | Category | Owner | Due | Evidence | Status | Decision (one sentence) | Impact (time/cost/risk) |
|---|---|---|---|---|---|---|---|---|
| D-014 | Standardise time-series granularity for EU/AU/UK/US | Design/Data | Architecture Lead | 2026-02-03 | Data model v0.6 + sample curves | Decided | Store 5-minute base, aggregate to local market intervals in services | +8 dev days now; avoids refactor later; reduces reconciliation risk |
| D-015 | Intraday exception handling: auto-recalc vs manual approval | Design | Front Office PO | 2026-02-03 | BPMN draft + workflow demo | Decided | Auto-recalc within thresholds; manual approval above thresholds | Faster ops; clear controls; prevents “silent automation” risk |
| D-016 | ERP posting: single summary journal vs per-trade detail | Design/Scope | Finance Lead | 2026-02-05 | Posting options doc + ERP constraints | Escalated | Steering to decide detail level by materiality threshold | Material control decision; affects close process + audit posture |
| D-017 | Counterparty golden source: CRM vs ERP vs CTRM master | Data | Data Lead | 2026-02-06 | Master data map + quality stats | Decided | ERP = golden for legal entity; CTRM for trading attributes | Cuts duplicate maintenance; reduces settlement break risk |
| D-018 | Market data vendor SLA requirement for intraday curves | Scope/Risk | Risk Lead | 2026-02-07 | Incident history + SLA options | Ready | Recommend SLA tier upgrade with penalty clauses | +$30–60k/yr; reduces pricing gaps and P&L disputes |
| D-019 | UAT entry criteria (test pass % + defect ceiling) | Test | Test Lead | 2026-02-10 | Test dashboard + defect taxonomy | Decided | Enter UAT at 85% pass; no Sev1 open; Sev2 ≤ 10 | Prevents “UAT is debugging” pattern |
| D-020 | Cutover sequencing: power first vs finance first | Cutover | Program Manager | 2026-02-12 | Cutover runbook v0.3 | Open | Options defined; needs sponsor call | Wrong sequence risks settlement breaks and month-end pain |
| D-021 | Side request: “just add a quick fee rule” | Scope | PM | 2026-02-12 | Email chain + effort estimate | Converted to CR | Treated as CR-007, not a decision | +4 days dev + retest; pushed to next release; protects go-live |
What to notice:
- Every row has an owner, a due date, and an evidence link.
- Side deals don’t get debated. They get converted into a CR with a price tag.
- Decisions that touch audit/control posture escalate cleanly.
4.3 Example “Decision Forum” agenda (weekly, 60 min)
Decisions due last week: Implemented? If not, why not?
Only items with a 1-page brief + evidence get airtime
Anything outside forum authority goes to Steering with a crisp ask
Old open items that keep coming back
What changes in backlog, build plan, test plan, training plan
4.4 Example metrics dashboard (what leadership sees)
Week ending 2026-02-07 (example):
- Decisions raised: 11
- Decisions made within SLA (5 business days): 8 / 11 (73%)
- Average decision latency: 6.2 days
- Decisions re-opened: 2 (both lacked evidence at first pass)
- Side deals detected and converted to CRs: 3
- Estimated rework avoided (from early escalation): ~14 dev days
That last line is the point: this is not “governance theatre”. It’s cost control.
5) Outcomes, risks, mitigations
Short-term outcomes (2–4 weeks)
Less ambiguity in meetings
Fewer reversals
Vendor stops “selling in the room” and starts showing evidence
Risk: the forum becomes another status meeting
Mitigation: no brief + no evidence = not discussed
Long-term outcomes (2–3 months)
A program that stops fragmenting
Clean accountability across business, IT, and vendor
A board update based on facts, not confidence levels
Risk: decision ownership gets “delegated into a void”
Mitigation: decision owner must be present; otherwise decision auto-escalates
Unexpected outcome (good)
Burnout drops because people stop doing the same alignment work twice
Risk: some people hate losing informal power
Mitigation: enforce the “no log = no decision” rule once, publicly, then it sticks
6) Rollout in five steps
- Name the forum + chair + authority thresholds
- Stand up the decision log and publish the rule: no log, no decision
- Run triage twice in week one to flush hidden decisions
- Run the first forum with only 3–5 “ready” decisions
- Publish the first metrics cut (latency + reopens + side deals)