Race to Go‑Live: Building a 100‑Day Critical Path
Part of the Implementary Traction™ methodology for high‑stakes go‑lives in energy & commodity trading
What this delivers
- A backward‑mapped 100‑day plan from an immovable go‑live date.
- Named owners and dated dependencies across Business, Technology, Data, and Change.
- A go/no‑go framework, cutover runbook, and hypercare plan that align to board or regulatory deadlines.
Preconditions (Do not start without these)
Entry criteria
- A fixed target go‑live date and a one‑sentence definition of “live.”
- Executive sponsor empowered to make scope/time/cost trade‑offs within 48 hours.
- Core team (PM, Tech Lead, Business/Change Lead, Data Lead, QA Lead) ≥ 80% allocated for 100 days.
- Scope guardrails: Phase‑1 must‑haves, deferrable should‑haves, explicit out‑of‑scope list.
- Decision and escalation SLAs: Triage (24h) → Sponsor (48h) → ExCo/Board (72h).
- One source of truth: A visible plan (Gantt or timeline), RAID log, decision log, and weekly status.
Tip: In a 100‑day race, clarity beats optimism. If any precondition is missing, either fix it now or add time.

Method in one page (for executives)
- Fix the finish: define the go‑live milestone from the board date backwards.
- Map from right‑to‑left: for each outcome, list the last prerequisite, then its prerequisite, and so on until today.
- Time it: add durations/lead times; identify parallelism and the critical path.
- Name it: assign one accountable owner and a calendar date to each task.
- Gate it: insert quality gates, go/no‑go criteria, and a rehearsed cutover runbook.
- Run it: daily/weekly rhythms, RAG health, hard change control, and “no surprises” escalation.
- Land it: go‑live weekend playbook and Day‑101 hypercare.
Roles & responsibilities (RACI‑style summary)
| Role | Owns | Accountable for |
| Executive Sponsor | Priority calls, scope trade‑offs, vendor alignment | Decisions ≤ 48h, unblockers, benefits realisation |
| Program/Project Manager | Master plan, RAID, governance cadence | On‑time/on‑budget delivery; critical path control |
| Technology Lead/Architect | Environments, integrations, builds, performance | Tech readiness, non‑functional criteria met |
| Data Lead | Migration, reconciliation, reference data | Data cut quality; sign‑off of balances/positions |
| Business/Product Owner | Requirements, UAT, process sign‑off | “Fit‑for‑purpose” and user adoption |
| Change/Training Lead | Comms, training, SOP updates | Training complete/readiness met |
| QA/Test Lead | Test strategy, automation, defect triage | Exit criteria (pass rates, severity thresholds) |
| Cutover Manager | Runbook, dress rehearsal, go‑live weekend | Smooth cutover and rollback readiness |

The workshops that build the plan (Week 1)
Workshop A | Define “Live”
- Output: one‑page “Definition of Live” (scope, users, locations, data date, interfaces, controls).
- Decisions: mandatory features versus deferrable.
- Timebox: 90 minutes.
Workshop B | Backward Mapping
- Method: Start with the go‑live card on the far right. For each “to be true at go‑live,” add the immediate prerequisite to its left. Repeat to today.
- Lenses: Tech, Data, Business Process, Change/Training, Compliance.
- Timebox: 2 × 90 minutes.
Workshop C | Durations & Owners
- Output: duration estimates, lead times (e.g., vendor 15 days, security reviews 10 days), one owner per task.
- Timebox: 2 hours.
Workshop D | Risk Pre‑mortem
- Prompt: “It’s Day 120 and we slipped, why?” Collect causes; convert to mitigations dated on the plan.
- Timebox: 60 minutes.
Workshop E | Cutover & Hypercare frame
- Output: first draft runbook phases (pre‑cut, cut, post), Day‑101 support model.
- Timebox: 90 minutes.

The 100‑Day schedule (baseline sprint)
Use this as the default; tailor with scenario variations below. Dates are calendar days unless stated.
Days 0–5 | Kickoff & baselining
- Confirm Definition of Live, governance cadence, escalation SLAs.
- Stand up tools: plan, RAID, decision log, status pack.
- Lock sprint/events cadence (see **7).
Days 6–15 | Right‑to‑left mapping & dating
- Complete backward map for all streams; add durations/lead times.
- Identify critical path; insert quality gates and go/no‑go checkpoints.
- Assign owners and calendar dates.
Days 16–45 | Build/Configure & Data ready (Sprints 1–2)
- Environments live; pipelines up; key interfaces stubbed.
- Core build/config (focus must‑haves only).
- Data migration trial #1 (subset) + reconciliation approach.
- Non‑functional baselines (performance, failover).
Days 46–75 | Integrate & Prove (Sprints 3–4)
- End‑to‑end happy paths working.
- Test cycles: SIT → UAT entry criteria met.
- Data migration trial #2 (full volume) + reconciliation runbook.
- Training content authored from frozen UI (change‑controlled).
Days 76–90 | UAT, Training, Dress Rehearsal
- UAT pass thresholds met (e.g., ≥95% pass; Sev‑1 = 0).
- User training ≥ 95% completion + competency checks.
- Cutover dress rehearsal in pre‑prod; measure timings.
Days 91–97 | Cutover Readiness & Go/No‑Go
- All exit criteria green; rollback tested.
- Formal go/no‑go (Sponsor + ExCo) with risk exceptions logged.
Days 98–100 | Cutover & Launch
- Execute runbook; smoke tests; business verification; comms.
- Begin hypercare.
Days 101–120 | Hypercare (stabilise)
- War‑room support; SLAs tightened; post‑go‑live fixes.
- Benefits tracking and close‑out retrospective.

Scenario variations (what changes)
A) ETRM/CTRM implementation
- Extra dependencies: market data adapters, trade capture, confirmations, risk calc windows, end‑of‑day batch, reporting, SOX controls.
- Data plan: instrument/curve master, open positions, historical P&L, back‑valuation checks.
- Gate: parallel run of daily P&L/risk (≥ 5 consecutive business days matching tolerance).
B) Digital platform deployment (integration‑heavy)
- Extra dependencies: API gateway, identity/SSO, event bus, observability, infrastructure as code.
- Non‑functional: throughput/latency SLOs, error budgets, auto‑scaling tests.
- Gate: chaos test (resilience) and failover drill.
C) Regulatory deadline go‑live
- Extra dependencies: regulatory interpretations, controls evidence, legal sign‑off, regulator notifications, parallel run, audit packs.
- Gate: regulator/assurance review package accepted; dry‑run of report submission with timestamped evidence.

- SIT exit: All Sev‑1/2 defects closed; Sev‑3 workaround documented; test coverage ≥ 85%.
- UAT entry: Feature set frozen; test data loaded; business scenarios signed; environments stable ≥ 5 days.
- UAT exit: ≥ 95% test pass, sero Sev‑1, ≤ 3 Sev‑2 with agreed workarounds; sign‑offs by Trading, Risk, Ops.
- Data readiness: Trial #2 reconciliation variance within tolerance (e.g., P&L ±0.5%; positions 0 variance).
- NFRs: 95th percentile response ≤ X ms on representative load; failover ≤ Y minutes RTO, ≤ s RPO.
- Training readiness: ≥ 95% completion; average score ≥ 80%; SOPs updated and acknowledged.
- Cutover readiness: Dress rehearsal completed; total window ≤ target; rollback executed successfully.
- Go/No‑Go: All gate sheets green or with signed exec exception + compensating controls.

Cadence & governance (run rhythm)
- Daily (15–20m): Stand‑up focused on critical path tasks only; blockers/escalations.
- Twice weekly (30m): Cross‑stream dependency review (PM + stream leads).
- Weekly (45–60m): Steering with Sponsor: RAG, deltas vs. plan, risk exceptions, decisions needed.
- Bi‑weekly: Demo/playback to key users/executives.
- Every 2 weeks: RAID scrub and forecast re‑baseline.
- Cutover countdown (T‑14, T‑7, T‑2): readiness checkpoints and drill reviews.
Change control (fast, firm, fair)
- Change request template: description, rationale, value, time/cost impact, risk, test/training impacts.
- Decision SLA: ≤ 48h by Sponsor; if ≥2‑day slip → defer to Phase‑2 unless regulatory/safety.
- Backlog: Park all approved deferrals in Phase‑2 with target date.

Risks & triggers (embed into plan)
- Typical top risks: environment delays, access/security reviews, data quality, vendor lead times, late scope adds, key‑person dependency.
- Early warnings: missed daily critical tasks; defect escape rates > threshold; UAT cycle slippage; training completion lag.
- Controls: second environment pathway; access pre‑checks; data profiling Day 10; vendor delivery milestones tied to payment; cross‑training plan.

Cutover & hypercare (operational detail)
Cutover weekend runbook (extract)
- Pre‑cut (T‑3d to T‑0): freeze code; final data snapshot; backups verified; comms to users; change tickets approved.
- Cutover (T‑0): deploy; data load; switch interfaces; smoke tests; business verification (trades, positions, reports).
- Post‑cut (T+0 to T+2d): hypercare activated; monitor; defect triage; daily exec updates.
Hypercare (Day 101–120)
- War‑room hours: extended; on‑call rota; severity matrix.
- KPIs: incident volume trend, MTTR, performance SLO adherence, user satisfaction pulse.
- Exit: 2 consecutive weeks within steady‑state thresholds; formal ops handover.

Real‑life “how‑to” checklists (copy/paste)
Daily critical‑path huddle (15 minutes)
- What critical path task is due today/tomorrow?
- Any blocker? If yes, who escalates and by when (clock starts now)?
- Any dependency we’re about to surprise another team with? Signal now.
Weekly steering
- RAG by stream + trend; explain any amber/red in one sentence.
- Delta vs. plan: tasks slipped ≥ 2 days?
- Decisions required this week (max 3); risks newly red; changes pending.
- Next gate readiness (tick‑box).
Dress rehearsal “done” check
- All steps executed in time order; timestamps captured.
- Rollback succeeded; total rollback time ≤ threshold.
- People/roles validated; comms templates used; monitoring alarms tested.

Templates (text you can drop into something like Confluence/Notion)
A) Task card (backward‑map standard)
- Outcome: (e.g., “UAT exit criteria met”)
- Immediate prerequisite: (e.g., “SIT exit met”)
- Owner (A): Name, role
- Support (R): Names
- Duration/Lead time: n days
- Start/Finish dates: dd‑mmm → dd‑mmm
- Acceptance criteria: bullet list
- Risks/Dependencies: bullet list
B) Gate sheet (example: UAT exit)
- Pass rate ≥ 95% ✔ / ✖
- Sev‑1 defects = 0 ✔ / ✖
- Sev‑2 ≤ 3 with workarounds ✔ / ✖
- Sign‑off: Trading, Risk, Ops (names, dates)
C) Change request (fast form)
- What/Why/Value:
- Impact (time/cost/risk):
- Decision by (date):
- Result: Approve to Phase‑1 / Defer to Phase‑2
D) Go/No‑Go pack sections
- Gate status summary (RAG)
- Defect matrix & top risks
- Cutover runbook ID + timestamped rehearsal results
- Exception list with compensating controls
- Sign‑off page

Example acceptance criteria (ETRM)
- Daily P&L parity: new vs legacy over 5 business days within ±0.5%.
- Trade capture: 100% of live asset classes supported; latency ≤ X ms.
- Confirmations: STP rate ≥ 98%; exceptions ≤ 2% within 24h.
- Reporting: end‑of‑day risk published by 18:00 local.
Example training readiness (Trading)
- 95% of traders completed 2‑hour module + passed 20‑question quiz (≥ 80%).
- Desk SOPs updated; runbooks printed at desktops.
Example non‑functional (Platform)
- 95th percentile response < 300ms at 2× peak load; autoscale test passes; RTO ≤ 15 min, RPO ≤ 5 min.
Example regulatory (Reporting)
- Dry‑run file validated by regulator portal; audit evidence stored with checksum and timestamp.

Real‑world patterns to borrow (optional callout boxes)
- Pre‑configured modules accelerate: choose out‑of‑the‑box where possible for a 100‑day window.
- Phase to win: get to a safe Phase‑1, then layer features; don’t chase perfection in Phase‑1.
- Collaboration beats contracts (during delivery): keep levers, but solve problems in the room first.
- Dress rehearsals save weekends: measure step timings; eliminate unknowns before T‑0.
What to publish vs. what to keep internal
- Public blog: this methodology, diagrammed plan, example gates, and high‑level runbook.
- Internal: costings, vendor clauses, detailed on‑call lists, system names/URLs, IP.
One‑page status pack (weekly – structure)
- Headline: “On track to Day 100: Yes/No. If no, why.”
- Milestone ladder (thumbnail of Diagram 1) with slipped tasks in red.
- RAG & trend (Schedule, Scope, Cost, Risk, Quality).
- This week vs. plan: 3 bullets done, 3 bullets next, 3 risks/actions.
- Decisions needed (max 3) with deadline/owner.
- Gate readiness checklist.
Frequently asked questions (coach your stakeholders)
- Q: Can we add Feature X now?
A: If it moves the plan by >2 days, it’s Phase‑2 unless regulatory/safety. - Q: Why is training on the critical path?
A: Because adoption risk can sink a “technically successful” go‑live. Readiness is a go/no‑go gate. - Q: What if the dress rehearsal fails?
A: Fix, re‑rehearse within 7 days, or move the go‑live date, don’t gamble production.

How to start this week (action plan)
Today
- Appoint Cutover Manager; confirm escalation SLAs; schedule Workshops A–E.
- Create the plan shell with lanes and gate placeholders.
Within 5 days
- Complete right‑to‑left map; add durations, owners, dates; mark critical path.
- Publish cadence calendar; start daily critical‑path huddles.
Within 10 days
- Lock gate criteria; finalise vendor lead times; set change control.
- Book dress rehearsal date; outline runbook.
Final note
This is a 100‑day operating system, not a slide deck. Keep it visible, keep it dated, keep it owned. If the plan changes, change the picture the same day.
About the Author
Jason Novobranec is Implementary’s Chief Operating Officer.
With over 20 years of Consulting, Program Management & Senior Leadership experience, Jason has delivered initiatives for large multi-national / multi-regional organisations as well as SME’s and is an expert in shaping solutions to fit a customer’s project needs.