Every change request needs a price tag
A late change request is not “a small tweak.” It’s a surcharge.
In commodity logistics, you don’t add a container after the vessel is sealed and pretend nothing changes. You pay for re-handling, slot risk, documentation updates, and knock‑on timing. The surcharge isn’t punitive. It’s reality.
Digital transformation works the same way. If you don’t price changes, you don’t avoid cost. You just hide it until testing, cutover, or hypercare.
So here’s the rule for execs: no CR gets approved without a visible price tag and a trade-off.
The Board‑Ready Change Pricing Template
Copy/paste this into your change log. Keep it to one page. Make it unemotional.
Change Request Pricing Card (one per CR)
- CR ID / Title:
- Requested by:
- Date raised:
- Decision needed by: (48h default)
1) What changes (plain English)
- Current behaviour:
- Proposed behaviour:
- Who is affected: (Trading / Ops / Risk / Finance / IT / Vendor)
2) Delivery price tag (time)
- Effort estimate: S / M / L (or days)
- Critical path impact: +0 / +1–2 / +3–5 / +>5 days
- Earliest safe release: (date)
3) Risk price tag (quality + controls)
Tick all that apply:
- ☐ Data model / master data
- ☐ Interfaces / message contracts
- ☐ Posting to ERP / settlement rules
- ☐ Valuation / risk calcs
- ☐ Access controls / segregation of duties
- ☐ Cutover steps / rollback plan
Overall risk: Low / Medium / High
4) People price tag (capacity + change)
- Extra SME time required: (hours / week)
- Extra test effort: (hours / week)
- Training impact: Low / Medium / High
- Operations impact during freeze / close: Yes / No
5) Evidence required (to approve)
- ☐ Updated workflow / BPMN snippet
- ☐ Test plan impact (must‑run pack changes)
- ☐ Cutover/runbook impact
- ☐ Updated acceptance criteria
6) The trade (mandatory)
Choose one:
- Swap: remove/defer ___
- Split: phase 2 on ___ (date)
- Spend: add ___ (people/budget) and accept ___ (date/risk)
- Stop: decline
- Decision: Approved / Deferred / Rejected
- Approver: (one name)
- Owner: (one name)
- Next checkpoint date: (date)
Scoring model execs can use in 90 seconds
If you want a simple score, use 1–5 on three axes:
- Time impact (1–5): does it hit critical path?
- Risk impact (1–5): does it touch Tier‑3 areas (data, interfaces, postings, access)?
- People impact (1–5): does it consume scarce SMEs, testing, or change capacity?
- Total score = Time + Risk + People (3–15)
Decision rule
- 3–6: approve if it has a named owner + evidence
- 7–10: approve only with a swap
- 11–15: defer unless it prevents a regulatory breach or operational failure
This isn’t “process.” It’s exposure control.
What this prevents
- “Small” changes that blow up testing
- Silent scope expansion that eats buffer
- Vendor optimism that turns into late‑stage surprises
- Unplanned SME load that burns out operations
Outcomes, risks, mitigations
Short-term outcome: steering meetings speed up; fewer emotional arguments.
Risk: stakeholders complain it’s bureaucracy.
Mitigation: show them the alternative: hidden cost paid at cutover.
Long-term outcome: you protect go‑live quality without grinding delivery to a halt.
Risk: decisions get pushed outside governance.
Mitigation: only approve CRs with a CR card ID; everything else is not work.
Unexpected outcome: vendors tighten estimates and reduce hand‑waving.
Risk: vendors push back on scoring.
Mitigation: require evidence and impact, not negotiation.
Five steps to implement this next week
- Publish the CR card template as the only intake format.
- Set a decision SLA (48 hours) and enforce it.
- Make swaps visible: “approved CRs must cite what moved out.”
- Trend the scores weekly: how much risk/time you’ve bought.
- Share a one‑page board view: “CRs approved, deferred, swapped, total score.”
Three questions to tune the template to your environment
- Do you prefer effort in days or S/M/L (with a conversion table)?
- What are your Tier‑3 “do not touch” areas during close/freeze: postings, data model, interfaces, access, or valuation?
- Who holds the single approval pen for CRs today?
Summary
Late changes behave like surcharges. Price them before you accept them. A simple CR card scoring time, risk, and people impact creates a board-ready change log, forces trade-offs, and protects quality and the timeline.