The Escalation Pack

1 page, 3 options (for trading platforms + ERP)

Escalations go wrong when they arrive as emotion.

They work when they arrive as evidence + choices.

Boards do not need another “we’re concerned.”

They need: what’s true, what it costs, and what decision unblocks delivery.

Below is a copy‑paste template, then a fully worked example in a commodity trading setting.

1) One‑Page Escalation Pack Template

  • Program:
  • Date:
  • Prepared by:
  • Decision needed by: (date + time)
  • Audience: (ExCo / SteerCo / CIO / COO)

A. Situation (1 sentence)

What happened and why it matters now:

Example format: “Cutover rehearsal shows settlement will miss the month‑end freeze window unless we change date/scope/resourcing this week.”

B. What changed (3 bullets, max)

  • New fact:
  • New constraint:
  • New risk:

C. Evidence (facts only)

Use numbers. Point to artefacts.

Delivery signals

  • Critical path item(s):
  • Decision blocked since: (date)
  • Earned vs burn: (value delivered vs spend to date)
  • Test pass rate: (%, by stream)
  • Sev1/Sev2 defects open: (# / #)
  • Data recon variance: (%, by domain)
  • Cutover rehearsal duration: (planned vs actual)
  • Change readiness: (training %, comms, SOPs ready Y/N)
  • Operational readiness: (runbook complete %, on‑call roster Y/N)

Evidence pack links (artefacts)

  • Demo video(s):
  • Test report(s):
  • Defect list snapshot:
  • Data recon report:
  • Cutover runbook + rehearsal log:
  • RAID log (risks, assumptions, issues, dependencies):

D. Impact if we do nothing (say it plainly)

  • Time:
  • Cost:

Risk: (customer / regulatory / financial / control)

E. The decision (one sentence)

We need a decision on: (date vs scope vs cost vs risk posture)

F. Options (pick 3 that are meaningfully different)

Option 1, Protect the date (accept scope reduction)

  • What we do:
  • What we get:
  • Trade‑offs:
  • Incremental cost:
  • Residual risk + controls:

Option 2, Protect the scope (move the date)

  • What we do:
  • What we get:
  • Trade‑offs:
  • Incremental cost:
  • Residual risk + controls:

Option 3, Protect scope + date (pay and control risk)

  • What we do:
  • What we get:
  • Trade‑offs:
  • Incremental cost:
  • Residual risk + controls:

G. Recommendation (one paragraph)

State the recommended option and why.

Call out what you will stop doing.

H. What happens in the next 72 hours (if approved)

  • Owner + action + deadline
  • Owner + action + deadline
  • Owner + action + deadline

I. Comms (keep it boring)

  • Who hears it first:
  • Who hears it next:
  • Message in one line:

2) Fully Worked Example

CTRM replacement + ERP integration (energy trading)

  • Program: CTRM Replacement + ERP Integration (Physical Power + Gas + Invoicing)
  • Date: 28 Jan 2026
  • Prepared by: Program Sponsor + Program Director
  • Decision needed by: 30 Jan 2026, 12:00 (to protect Feb market + month‑end freeze)
  • Audience: COO, CFO, CIO, Head of Trading Ops, Vendor Delivery Lead

A. Situation (1 sentence)

Cutover rehearsal shows we cannot complete end‑to‑end settlement + invoicing inside the month‑end freeze window, unless we change date, scope, or resourcing this week.

B. What changed (3 bullets)

  • New fact: Rehearsal run time = 14h 20m vs allowed window 8h 00m (freeze starts 22:00).
  • New constraint: Two vendor SMEs (market data + settlement) unavailable in week of cutover due to parallel client go‑live.
  • New risk: Data reconciliation variance in positions + prices exceeds tolerance in two domains, increasing mis‑statement risk.

C. Evidence (facts only)

Delivery signals

Critical path item(s):

  • Market data + curve ingestion stability (intraday + day‑ahead)
  • Settlement calculation parity (legacy vs new)
  • ERP invoice interface + GL posting validation

Decision blocked since: 17 Jan 2026 (scope decision on “phase derivatives later” not made)

Earned vs burn:

  • Spend to date: AUD 2.4m
  • “Done” by evidence: Core deal capture 90%, settlement 70%, invoice/GL 55%

Test pass rate:

  • SIT overall: 78% pass
  • Settlement stream: 71% pass
  • ERP interface stream: 63% pass

Sev1/Sev2 defects open: Sev1 = 6, Sev2 = 19

Data recon variance:

  • Positions (MWh) variance: 1.9% (tolerance 0.5%)
  • Price curves variance: 0.7% (tolerance 0.2%)
  • Counterparty master mismatches: 112 records

Cutover rehearsal duration:

  • Planned: 8h
  • Actual: 14h 20m
  • Top drivers: ERP batch timing + rework loops in settlement validations

Change readiness:

  • Role‑based training complete: 52% (target 90% pre‑cutover)
  • SOPs signed off: 6/18 complete

Operational readiness:

  • Runbook complete: 65%
  • On‑call roster: Drafted, not confirmed (Ops + IT + vendor)

Evidence pack (artefacts)

  • Demo video: “E2E trade → settlement → invoice (happy path)” (12 min)
  • SIT report: “SIT Cycle 3 Summary”
  • Defect list: “Sev1/Sev2 Snapshot 28 Jan”
  • Data recon: “Legacy vs New Parity Report”
  • Cutover rehearsal log: “Rehearsal #1 Timeline + Issues”

D. Impact if we do nothing

  • Time: Cutover overruns the freeze window; rollback likely; next slot slips by 2–4 weeks.
  • Cost: Extended hypercare + duplicate run costs AUD 180k–260k.

Risk: Settlement/invoicing errors; increased manual corrections; audit and governance exposure at month‑end.

E. The decision

Decide whether we protect the go‑live date, protect full scope, or protect risk controls, and lock one plan by Friday.

F. Options (three that actually differ)

Option 1, Protect the date (reduce scope now)

What we do

  • Go‑live physical power + gas deal capture + nominations.
  • Defer ERP invoice automation and run manual invoice + GL posting for 4–6 weeks.
  • Defer complex settlement scenarios (e.g., bespoke fee logic) to Sprint 2 post go‑live.

What we get

  • Hit the board date.
  • Stop bleeding calendar time.

Trade‑offs

  • Higher ops load and reconciliation effort.
  • Manual controls must be tight.

Incremental cost

AUD +120k (ops overtime + controls + hypercare)

Residual risk + controls

Risk: Manual invoice mistakes.

Controls: Dual sign‑off, daily reconciliation, exception queue, audit trail.

Option 2, Protect the scope (move the date)

What we do

  • Slip go‑live by 3 weeks.
  • Run rehearsal #2 and #3.
  • Close Sev1 to zero and bring SIT pass rate to ≥95% in settlement + ERP.

What we get

  • Cleaner cutover, lower defect carryover, less “surprise debt.”

Trade‑offs

  • Board date moves.
  • Team fatigue risk if pace stays frantic.

Incremental cost

AUD +240k (extended vendor + internal team)

Residual risk + controls

Risk: Confidence hit if message is messy.

Controls: Clear escalation narrative + weekly demo proof.

Option 3, Protect scope + date (pay and control risk)

What we do

  • Add a dedicated vendor “tiger team” for 10 business days (market data + settlement + ERP).
  • Run parallel extended shift for test and data recon.
  • Implement strict WIP limit: stop starting features; finish parity + runbook.

What we get

  • Chance to hold date without cutting scope.
  • Keeps automation objective intact.

Trade‑offs

  • Costs more.
  • Still carries risk if decision latency continues.

Incremental cost

AUD +310k (vendor surge + extended hours)

Residual risk + controls

Risk: Throwing people at chaos.

Controls: Daily decision forum, single decision log, zero side deals.

G. Recommendation

Recommend Option 2 unless the board date is immovable for external reasons.

The evidence says parity + ERP readiness are not there yet, and a single “hero” cutover invites a settlement mess that will land on Ops and Finance at month‑end. If the date cannot move, take Option 1 and be honest: ship a safe slice, control it hard, then automate properly.

H. Next 72 hours (if approved)

  • CFO + Head of Ops: Confirm month‑end freeze window and manual control requirements (by 29 Jan EOD)
  • Vendor Delivery Lead: Staff surge team or confirm slip plan (by 29 Jan 12:00)
  • Program Director: Publish revised critical path + decision calendar (by 30 Jan 09:00)

I. Comms

  • First: Sponsor → ExCo (15 minutes)
  • Then: Program → all stream leads (30 minutes)
  • One‑line message: “We’re choosing a controlled outcome over a dramatic one.”

3) How to use this pack (5 steps)

  • Collect evidence (test, data, runbook, rehearsal). No evidence, no escalation.
  • Write the situation in one sentence. If it takes a paragraph, it’s not clear.
  • Build three real options. If two options are the same with different adjectives, start again.
  • Pre‑align privately. Nobody likes surprises in a steering meeting.
  • Decide once, log it, and stop side deals. One log, one owner, one date.

Weekly Newsletter

Get the Weekly Implementary Insights Wrap Up PDF every Friday.

Privacy: We will not use your contact information for any purpose other than sending this Newsletter.
Unsubscribe anytime with one click from any email.
Published On: January 28th, 2026 / Categories: Transformation /