UAT attendance is a vanity metric
If your UAT plan “looks healthy” because 40 people turned up, you’re already in trouble.
Because UAT isn’t a meeting.
UAT is proof. Proof that the trade lifecycle runs end‑to‑end, with known risk, and with evidence you can defend when something breaks at 02:00.
Counting attendees is like counting ships in harbour. It tells you activity exists.
It tells you nothing about whether the cargo delivered, the bill of lading matches, or the customer got paid.
So here’s the move: stop measuring presence. Start measuring acceptance.
The real issue
In commodity trading tech, “UAT is underway” often means:
- People click around modules.
- Defects get logged, but nobody agrees what “done” looks like.
- A few loud users dominate the narrative.
- The program drifts into “good enough” because the deadline does not move.
Then Monday happens.
Ops starts “chasing ghosts.” Traders export to spreadsheets. Finance pulls manual reconciliations. The vendor says “UAT signed.” Everyone argues about what “signed” meant.
That is not a testing problem.
That is an evidence problem.
The outcome you actually want
Honest readiness signals.
Not comfort. Not optimism. Not “green” dashboards built on headcount.
Readiness means:
- Critical scenarios run
- Defects found early
- Retests pass clean
- Sign‑offs exist with names and dates
- Known risks sit in one place with an owner
Mini‑guide: 5 steps to measure UAT like a control room
Define “done” as cargo delivered, not ship departed
Write one sentence that UAT must prove:
“This desk can run real trades from capture → risk → confirmations → settlement with acceptable defects, and the evidence pack exists.”
Then lock three UAT artefacts as non‑negotiable:
- Signed scenarios (by business owners, not only IT)
- Defect log with severity and aging
- Retest evidence (pass/fail with timestamps)
If a scenario runs but nobody signs it, it does not count.
Track four metrics that do not lie
Use these weekly. Put them on one page.
- Signed scenario rate
Definition: # scenarios signed / # scenarios planned for the sprint
Signal: coverage and acceptance - Retest pass rate
Definition: # defects retested and passed / # defects retested
Signal: fix quality - Defect aging by severity
Definition: median days open for P1/P2/P3
Signal: stall and hidden debt - Scenario stability
Definition: # scenarios that pass twice in a row without workarounds
Signal: repeatability
Attendance is not a metric.
Headcount is not evidence.
Build a UAT scoreboard that the business recognises
Here’s an example worksheet (filled with realistic data) for a cross‑commodity rollout where UAT covers physical, derivatives, and settlement.
UAT Scoreboard – Week ending 2026‑02‑14 (example)
| Lane | Scenario | Owner sign-off | Run count | Last result | Open defects linked | Retest pass rate | Notes |
|---|---|---|---|---|---|---|---|
| Physical oil | Crude FOB cargo: capture → nomination → BL → invoice | A. Rahman (Back Office) | 2 | Pass | 3 | 67% | Invoice tolerance rule missing for FX rounding |
| Power | Power swap hedge → risk limits → P&L close | S. Nguyen (Risk Control) | 3 | Fail | 5 | 40% | Duplicate deal IDs on replay |
| Metals | LME futures execution → confirmation → clearing match | J. Wong (Trading Ops) | 2 | Pass | 1 | 100% | One mapping fix pending deployment to UAT |
| FX | USD/JPY hedge → confirmation matching → settlement | T. Chen (Treasury Ops) | 2 | Fail | 4 | 50% | Late confirmations not linked to Payment_ID |
| Finance | ERP posting → accruals → settlement reconciliation | M. Patel (Finance Ops) | 1 | Fail | 6 | 33% | Cost centre mapping not in master data |
Now add a simple weekly roll‑up:
UAT Roll‑up – Same week (example)
| Metric | This week | Last week | Threshold | Status |
|---|---|---|---|---|
| Scenarios planned | 18 | 16 | ||
| Scenarios executed | 14 | 12 | ≥ 80% | Amber |
| Scenarios signed | 7 | 5 | ≥ 60% | Red |
| Retest pass rate | 58% | 61% | ≥ 80% | Red |
| P1 defects open | 4 | 3 | 0 | Red |
| Median age P2 defects | 9 days | 6 days | ≤ 5 days | Red |
That is a real conversation starter.
It also makes the problem visible: not “more people needed.” The issue is sign‑off and fix quality.
Run UAT as a 15‑minute control room, not a 60‑minute status show
Agenda. Same every week. No theatre.
- Evidence: what scenarios got signed this week
- Defects: top 5 by severity + age
- Retest: what passed twice
- Decisions needed: 1–3 items max, named owner, date
- Next demo: which end‑to‑end lane runs next
Two rules:
- No scenario discussion without the scenario ID.
- No “we’re on it” without an owner and a date.
Stop “UAT waivers” from becoming unpriced risk
Waivers happen. The problem is silent waivers.
Set waiver rules that fit trading reality:
- A waiver needs impact (what breaks), containment (how you limit damage), and expiry (when it gets fixed).
- A waiver needs a named owner who signs it, not a committee.
- A waiver needs a monitor (what metric flags it going wrong).
Example waiver entry (filled):
| Waiver ID | Scenario impacted | Defect | Business impact | Containment | Owner | Expiry |
|---|---|---|---|---|---|---|
| WV‑UAT‑014 | FX hedge match → settlement | Payment_ID not populated for partial invoices | Manual matching in Treasury Ops | Daily unmatched report + stop rule at 20 items | Treasury Ops Lead | 2026‑03‑06 |
Now the risk has a price tag: people time, reconciliation noise, and settlement exposure.
Short, long, unexpected outcomes
Short outcome
Faster truth. Less arguing. UAT becomes a set of artefacts, not opinions.
Risk: the dashboard looks “worse” for two weeks.
Mitigation: treat it as visibility, not failure. Fix the top defect driver first.
Long outcome
Fewer go‑live incidents because the team proves repeatability.
Risk: vendor resists evidence standards.
Mitigation: tie acceptance and milestone payments to evidence packs, not effort.
Unexpected outcome
Business trust rises because IT stops asking for “more UAT attendance” and starts showing control.
Risk: some stakeholders lose influence when the loudest voice stops driving priorities.
Mitigation: keep decisions in one log. Make sign‑off rules public.
If you want weekly momentum, turn this into a Reset Plan
If your UAT currently runs on vibes, convert it into a Reset Plan: actions, owners, dates, vendor accountabilities.
Start with these three lines:
- Top 10 scenarios that represent your real book
- Weekly UAT scoreboard with thresholds
- One decision log with owners and dates